|
Activity Report
April
19, 1996 Prepared by Pacific Northwest National
Laboratory, Richland, Washington
RUSSIA Confinement Isolation Project. Nine of
eleven confinement isolation valves have been installed at the Kola
nuclear power plant (NPP). Staff from Burns & Roe are helping with the
installation, which is estimated to take approximately one month.
Brookhaven National Laboratory (BNL) ordered additional gasket material
required to complete the sealing of Kola Unit 2. The material will be
shipped by air to reach the plant before the end of the current outage.
The plant is scheduled to return to operation on May 18, 1996. To
determine how effectively the application of sealant and gasket material
has reduced leakage, the plant intends to perform confinement leak-rate
tests in May. Radiation monitors are another element of the Kola
confinement upgrade effort. The monitors were delivered to the plant the
week of April 8, and the cesium radiation source to be used in calibrating
the monitors is being packaged for shipment. (Rich Denning, PNNL,
614-424-7412) Safety Parameter Display Systems for RBMKs.
parsons Power/Gilbert Commonwealth signed a contract with Pacific
Northwest National Laboratory to provide safety parameter display systems
for ten operating RBMK reactors in Russia and Ukraine. The systems are
similar to those being provided to the Kursk NPP Unit 2. Work will begin
immediately to identify plant-specific differences that will affect the
design of the safety parameter display system for each plant. The next
NPP to be provided with a safety parameter display system will be
Chornobyl Unit 3. (Rich Denning, PNNL, 614-424-7412/Rich Reister, DOE,
301-903-0234) Kola and Kalinin Full-Scope Simulators. S3
Technologies performed hardware acceptance tests on the Kola and Kalinin
NPP computer complexes on April 3 and 4, 1996, at Columbia, Maryland.
Each computer complex consists of server(s), workstations, personal
computers, and accessories. The tests were largely successful. S3
Technologies is resolving minor problems encountered, which were
associated with a new version of the Irix operating system. In addition,
S3 Technologies staff demonstrated the use of the executive software on
the Kalinin simulation computer (SGI Power Challenge L with four R8000
CPUs). However, the execution of a generic VVER NPP simulator model on
the Kola and Kalinin simulation computers was not successful. S3
Technologies has resolved these problems, and it will not delay either the
project schedule or shipment overseas. General Energy Technologies
(GET), the simulation model contractor, has requested detailed shipping
invoices from S3 Technologies for the Kola and Kalinin computer complexes
to avoid Customs problems. S3 Technologies is preparing these documents.
Additionally, GET has requested a letter from PNNL to the Agency of
Technical Cooperation with Russia (US Embassy, Moscow) and support from
DOE to have the Agency of Technical Cooperation with Russia send the
necessary letter to the Humanitarian Help Commission in Moscow, Russia.
It is hoped these measures will allow the equipment to flow smoothly
through the Customs process. Successful completion of the computer
tests and the receipt of Customs related documents will allow the
full-scope simulator computer complexes to be shipped to GET. Once the
equipment is delivered, GET can initiate the development of the actual
simulator models for the Kola and Kalinin NPPs. (Peter Kohut, BNL,
516-344-4982) UKRAINE Fuel Cycle Safety. The cask
transporter, which arrived in Ukraine in early January, has been released
from the Customs holding area at the Zaporizhzhya NPP. Duke Engineering
and Services (DE&S) is planning to have people there on Monday, April 22,
to begin inspection of the transporter, to train plant staff in its use,
and to facilitate acceptance of the transporter by the Zaporizhzhya NPP
staff. All remaining DE&S hardware supplied under the DOE contract
has been delivered to the plant and has been put into a Customs holding
area, with the exception of the multi-assembly sealed baskets. DE&S will
try to have the equipment released from Customs while they are at
Zaporizhzhya NPP for transporter acceptance tests. (Mike McKinnon, PNNL,
509-372-4198) Khmelnytskyy Full-Scope Simulator. Recently DOE
and Goscomatom signed an agreement to identify the requirements for
obtaining Ukrainian Customs clearance. However, there is more information
required in order for S3 Technologies to obtain release of one unopened
shipment at Energotraining that contains material needed to complete the
control panel modifications at Khmelnytskyy NPP. PNNL has sent the
necessary additional information. (Peter Kohut, BNL, 516-344-4982)
Training Activities. Chornobyl staff completed intensive
training in the Systematic Approach to Training methodology and instructor
techniques at General Physics in Aiken, South Carolina. They completed a
validated task list for the control room reactor operator position. This
will allow work to continue on the development of the control room reactor
operator training program. (Sonja Haber, BNL, 516-344-3575) Safety
Parameter Display Systems for RBMKs. See item under "Russia."
PLANNED ACTIVITIES * April 17-24 -- Rivne NPP,
Ukraine. A team with representatives from DOE, BNL, PNNL, S3
Technologies and Goscomatom will visit the Rivne NPP and Hartron
Industries in Kharkov. Discussions will address the construction of the
Rivne Operator Training Center and the Rivne full-scope simulator.
The NPP has contracted with Hartron Industries to construct the
simulator control room panels. The team will assess the manufacturing
capabilities of this facility. (Peter Kohut, BNL, 516-344-4982)
April 19-28 -- Visaginas, Lithuania. The
U.S.-sponsored workshop on Preventive and Predictive Maintenance in
Nuclear Power Plant Operation will be conducted at the Ignalina NPP.
Staff from ANL, DOE, PNNL, and representatives from the RBMK NPPs
will attend. This workshop is part of a series aimed at enhancing the
operational safety of NPPs in Central and Eastern European countries.
(Grig Trosman, DOE, 301-903-3581) April 20-25 -- Moscow,
Russia. Representatives from DOE and BNL will attend meetings
to develop a work plan for technology transfer activities on the
Systematic Approach to Training. (Dan Giessing, DOE, 301-903-2852)
April 21-26 -- Moscow, Russia. The Kola in-depth
safety analysis (KOLISA) project team will meet in Moscow, Russia, to
develop project plans and guidelines, and to monitor progress. (Walt
Pasedag, DOE, 301-903-3628) April 21-26 -- Moscow, Russia.
Representatives from the Kurchatov Institute, Minatom, BNL, and the
Leningrad NPP will initiate the RBMK site-specific decommissioning
study. This project is a joint U.S.-Russian effort to: - develop a
safe, technically feasible, time-phased decommissioning strategy for
Leningrad Unit 1 (Unit 1 is a first-generation RBMK reactor)
- perform
the initial analyses to identify and characterize the regulatory and
technical plans required to support the above strategy.
The
participants will determine the details of the study and specify project
tasks, schedules, milestones, and deliverables. (Rich Reister, DOE,
301-903-0234) April 21-27 -- Sofia, Bulgaria.
BNL staff will provide technical assistance to the staff of the
Kozloduy NPP in the development of plant models to evaluate design
changes, review EOIs, and perform safety analyses for plant operations.
(Dan Giessing, DOE, 301-903-2852) * April 23-24 -- DOE,
Germantown, Maryland. Representatives from the Nuclear
Regulatory Commission (NRC), DOE, and PNNL will review comments
received on the Fire Safety Analysis, Reactor Core Protection Evaluation
Guidelines and determine appropriate responses. (Rich Reister, DOE,
301-903-0234) * April 23-27, 1996 -- Moscow, Russia.
Staff from BNL and Minatom will prepare a work plan for technology
transfer of International Nuclear Safety Program (INSP) training
activities. A future meeting with representatives from other plants in
Russia will be scheduled. (Sonja Haber, BNL, 516-344-3575) *
April 23-26, 1996 -- Moscow, Russia. The first bilateral
meeting on the RBMK site-specific decommissioning study is scheduled at
the Kurchatov Institute in Moscow. Programmatic details of the study
will be finalized during this meeting. The Leningrad NPP Unit 1 has
tentatively been selected as the site for analysis; however, the site
selection has not been finalized. (Bob Lavelle, BNL, 516-344-7747)
* April 25-May 8 -- Stockholm, Sweden. A
Swedish-sponsored emergency operating instruction (EOI) workshop will be
conducted in Stockholm, Sweden. Participants will include
representatives from Sweden, Lithuania, Russia and PNNL. Workshop
participants will work to resolve current EOI development issues, prepare
support documentation, and establish a training program. (Sam McKay,
PNNL, 509-372-4059) * April 29-May 3, 1996 -- Columbia,
Maryland. A technical exchange meeting regarding the
Chornobyl analytical simulator is tentatively scheduled for the week
of April 29. The intent of this meeting is to develop a detailed scope of
the Chornobyl analytical simulator project. (Peter Kohut, BNL,
516-344-4982) * May 1-2, 1996 -- Columbia, Maryland.
Staff from S3 Technologies, BNL, PNNL and the Novovoronezh NPP will
discuss the technical details of a contract for the Novovoronezh
analytical simulator. A representative of the Russian regulator,
Gosatomnadzor, may also attend. This meeting will finalize the scope
and technical requirements that will be included in the contract PNNL
will issue for the simulator. (Peter Kohut, BNL, 516-344-4982) *
May 6-9 -- Pennsylvania State University , State College,
Pennsylvania. The American Nuclear Society is sponsoring an
International Topical Meeting on Nuclear Plant Instrumentation and
Control, which includes a speech by NRC Chairman Shirley Jackson.
Representatives from DOE, PNNL, and the Electric Power Research
Institute (EPRI) will attend. DOE is also sponsoring three Russian
representatives to attend this meeting. (Rich Reister, DOE,
301-903-0234) May 11-17 -- Moscow, Russia.
Representatives from DOE and PNNL will participate in the Organization
for Economic Cooperation and Development (OECD) support group
meetings. This group is studying the safety research needs for the VVER
and RBMK reactors. (Colette Brown, 301-903-6924) May 11-25 --
Balakovo NPP, Russia. Balakovo NPP staff and Sonalysts
personnel will continue development of the Electrical Operations and
Instrumentation and Control Operations pilot training courses as well as
the Administrative Procedures Manual and Simulator Instructor
specialized training projects. (Sonja Haber, BNL, 516-344-3575) *
May 11-25 -- Kyiv and Slavutych, Ukraine. In Kyiv, staff from
DOE and PNNL will meet with representatives of Goscomatom to discuss
possible projects relating to licensee event reporting and the
Ukraine quality assurance program. At Slavutych, Chornobyl NPP will
host meetings of the RBMK EOIs working group. (Dennis Meyers, DOE,
202-586-7834) * May 12-16 -- Moscow, Russia. EOI
analytical work performed by VNIIAES, Gidropress, and the Kurchatov
Institute in support of VVER 440/213 plants will be the focus of
meetings to be held in Moscow. U.S. industry representatives will be
available to present EOI analysis methodology and offer strategy
suggestions. U.S. project representatives will attend to discuss
current and future tasks involved in this effort. (Walt Pasedag, DOE,
301-903-3628) * May 12-19 -- Moscow, Russia. PNNL
Contracts staff will meet with MOHT regarding 1) EOI contracts and tasks
associated with analytical work performed by VNIIAES, Gidropress, and
the Kurchatov Institute in support of VVER 440/213 EOIs, and 2)
contracts for the Novovoronezh NPP emergency water supply project.
Meetings will also be held with Rosenergoatom about contract issues.
(Doug Dahl, PNNL, 509-375-6855) * May 13-14 -- Kyiv, Ukraine.
Representatives of DOE, PNNL, and EPRI will meet with Goscomatom
to reach a final position on the safety significance of a Ukrainian
requested project for an In-Core Control and Monitoring System (ICCS) for
VVER-1000 plants. The team also will initiate new projects in
instrumentation and control, specifically the safety parameter
display systems for Rivne. (Rich Reister, DOE, 301-903-0234) *
May 14-15 -- DOE, Germantown, Maryland. The fire safety
working group will complete the resolution of comments received on the
Reactor Core Protection Evaluation Guidelines. The group will also
plan the training and implementation of the guidelines at nuclear
plants in Russia and Ukraine. (Rich Reister, DOE, 301-903-0234)
May 14-17 -- Chornobyl NPP, Ukraine. General Physics staff
will travel to the Chornobyl NPP to continue work on training programs.
(Sonja Haber, BNL, 516-344-3575) May 20-31 -- Aiken, South
Carolina. Staff from the Khmelnytskyy NPP and General
Physics will continue development of the Chemical Operator
Pilot Training Course. (Sonja Haber, BNL, 516-344-3575) * June 3-7
-- Moscow, Russia and Kyiv, Ukraine. DOE, BNL and PNNL
representatives will complete agreements with fire safety experts in
Russia and Ukraine concerning the implementation of the Reactor Core
Protection Evaluation Guidelines. With the planned completion of the
final guidelines and these agreements, work can begin on the evaluations
at specific plants in Russia and Ukraine. (Rich Reister, DOE,
301-903-0234) * June 3 -- Rivne NPP, Ukraine. The VVER
440/213 working group will hold its quarterly meeting at Rivne NPP. The
group will review EOIs produced at participating NPPs, NPP training
plans, and NPP plans for verification and validation of EOIs. U.S.
utility representatives will present the U.S. methodology on related
topics. The meeting will also follow up on outstanding issues from
the last meeting in November 1995. The working group will review
information from the EOI analysis meeting held in Moscow, Russia, in
May. (Larry Sherfey, PNNL, 509-372-4080) --------------- "*"
indicates the event is a new item or has been changed from the last
report. Note: in the interest of providing a timely update on the
Soviet-Designed-Reactor Safety Program, no formal document review of this
weekly report has been conducted by DOE or PNNL.
|
|