Important Note: This website contains historical data from the INSP project. As of 2004 the site is no longer maintained and certain sections do not work correctly.

INSP Logo
Chornobyl Initiatives Reports and Publications Photo Library Nuclear Reactor Profiles and Accomplishments About our Program Web site sections
- Current Activity Report
- Activity Report Archive
- Current Chornobyl Report
- Program Reports
- Brochures/Fliers
- INSP Resource Center


April 1999 - Armenia
- Bulgaria
- Czech Republic
- Hungary
- Kazakhstan
- Lithuania
- Russia
- Slovakia
- Ukraine
- United States
- Cross-Cutting Activities
- Planned Activities
- Previous Activity Reports



The April Activity Report documents safety improvements achieved in late March and April at Soviet-designed nuclear power plants through U.S. and host-country cooperation. To request a hard-copy version or to provide comments or suggestions, send an e-mail message to andrea.currie@pnl.gov.

Highlight of the Month

First Plant-Specific Risk Assessment Completed in Ukraine. On April 20, experts from South Ukraine nuclear power plant (NPP) and its contractor Energorisk presented the results of the first in-depth, plant-specific probability risk assessment (PRA) carried out in Ukraine. At a nuclear power plant, a PRA helps determine the most significant risks and set priorities for safety upgrades. The presentation was part of a two-day technical meeting of the Ukraine International Safety Assessment Steering Committee.

The Ukrainian presenters concluded that the results of the PRA will have a significant impact on the operational safety of the VVER-1000/302 units at South Ukraine NPP. Some preliminary insights gained include

  • Risk at the plant is dominated largely by operator actions. Symptom-based emergency operating instructions are needed to support consistent operator actions in an emergency.

  • Hardware-related risks include the inability to inject coolant via a high-pressure injection system during low-pressure accident conditions. The clogging of sump intake filters due to dispersion of pipe insulation during loss-of-coolant-accident conditions was found to contribute to the risk.

The PRA uncovered a number of problematic design features. One design problem could lead to failure of the backup emergency power supplies to a low-pressure injection system, if off-site power is lost. The problem is that the coolant system for the relevant electrical equipment is not linked into the emergency power supply. If off-site power failed, the electrical equipment could overheat and the low-pressure injection system would lose power. In addition, the control of gate valves at all three emergency feedwater systems would be lost during the short circuit of one direct current busbar. Although these issues are serious, the implementation of design changes would be relatively inexpensive.

Experts from South Ukraine NPP demonstrated the importance of plant involvement by becoming the first nuclear power plant in Ukraine to complete a plant-specific probabilistic risk assessment.

As follow-up to the preliminary studies, additional studies and an external review will be completed. However, even these preliminary studies demonstrated the value of carrying out in-depth, plant-specific safety assessments with plant involvement. In fact, plant experts hope to make PRA into a continuous process for monitoring risk, for example by adding a risk monitor at the plant.

During the second day of the meeting, U.S. and Ukrainian specialists discussed issues related to safety assessment of reactor containment and its engineered safety features. The U.S. specialists proposed transferring technology to address these issues to two plants, Zaporizhzhya Unit 5 and Rivne Unit 1. Energoatom is reviewing the proposal. (Walter Pasedag, DOE, 301-903-3628; Jeff Binder, ANL, 630-252-7265)

^top

Russia

Control Room Reactor Operator Training Courses Implemented at Two Plants. During April, training specialists implemented the Control Room Reactor Operator pilot course at both Novovoronezh and Smolensk NPPs. Training specialists from Balakovo NPP assisted Novovoronezh and Smolensk trainers in finalizing and implementing the course. Collaborating in the transfer were representatives of Sonalysts, Inc., Human Performance Analysis Corp., and the U.S. team. Implementation of these courses marks the transfer of the second of two training programs to both Novovoronezh and Smolensk NPPs as part of the U.S. effort to transfer training technology to nuclear power plants in Russia. (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)

Russian Plants Receive Inservice Inspection Equipment. As part of a collaborative effort to establish an in-service inspection process for nuclear power plant components, the U.S. team is providing critical technology needed to implement inservice inspection programs at all participating Soviet-designed nuclear power plants in Russia. In March, Balakovo and Kursk NPPs received their respective shipments of manual ultrasonic equipment. Earlier in 1999, shipments of the same equipment reached Novovoronezh, Leningrad, Kola, and Kalinin NPPs. At the end of April, arrangements were being finalized to deliver the devices to Beloyarsk, Bilibino, and Smolensk NPPs. Plant specialists will use the equipment in their inservice inspections to help ensure the integrity of nuclear power plant piping and components during a plant’s operating lifetime. (Tom Taylor, PNNL, 509-375- 4331)

Protective Clothing Being Delivered to Russian Plants. The U.S. team is providing two types of high-temperature suits to Russian nuclear power plants for use in emergency situations. The SZO-1 suits, manufactured by the Russian organization Zashitnaya Odezhda, are for use by firefighters or repair personnel in areas of extreme heat and in the presence of ionizing radiation. Plant personnel will use the Sukhovey suit, manufactured by Kentavr, another Russian enterprise, when making emergency repairs in high steam environments.

Firefighters and repair technicians at Russia’s nuclear power plants will wear this U.S.-provided protective suit in emergency situations involving high temperatures and ionizing radiation. The Russian enterprise Zashitnaya Odezhda manufactures the SZO-1 suit pictured here.

The United States has ordered 12 of the SZO-1 suits and 16 of the Sukhovey suits for delivery to Russian plants. Each suit is fabricated separately.

To date, Zashitnaya Odezhda has manufactured and delivered six of the SZO-1 suits to Smolensk, Balakovo, and Novovoronezh NPPs. Suits for the Balakovo and Novovoronezh plants arrived during March 1999. As of the end of April, Kentavr has provided eight of the Sukhovey suits to the Kalinin, Kursk, Balakovo, and Novovoronezh plants. (Rich Denning, PNNL, 614-424-7412)

Smolensk To Benefit from Circuit Breaker Technology Transfer to Russian Enterprises. On April 6, 7, and 8, U.S. team members from the U.S. Department of Energy (DOE) and Pacific Northwest National Laboratory met in Moscow with representatives of Rosenergoatom, Smolensk NPP, and Russian contractors ELOX and Plant Progress to discuss the circuit breaker technology transfer project. Participants reviewed progress on the 6-kilovolt breaker task, resolved outstanding contracting issues on the high-amperage 400-volt breaker task, and planned specific activities for the molded-case 400-volt breaker task.

Circuit breaker system under development for nuclear power plants in Russia consists of a 6-kilovolt breaker and associated trolley. The Russian enterprise ELOX will manufacture and obtain Russian Federation certification for units similar to the prototype assemblies pictured here. Smolensk NPP is the pilot site for system installation.

ELOX is making excellent progress toward certification of the 6-kilovolt circuit breakers. Certification by the Russian Federation is expected before the end of September 1999. Plant Progress will begin its certification process for the large-amperage 400-volt circuit breakers in May and expects to achieve certification also before the end of September.

Rosenergoatom identified Western Services to assist in coordinating the engineering activities necessary to design and install approximately eighty 400-volt molded-case circuit breakers into Smolensk NPP by early July 1999. (Norman Fletcher, DOE, 301-903-3275; Ron Wright, PNNL, 509-372-4076)

Detailed Planning Under Way for Novovoronezh Safety Assessment. Novovoronezh plant representatives met in Moscow on April 7 and 8 to plan for preparing a report to Gosatomnadzor on the in-depth safety assessment begun recently for Novovoronezh Units 3 and 4. Participating in the meeting were specialists from Science Applications International Corporation and DOE’s Argonne and Pacific Northwest national laboratories. Experience gained and lessons learned in preparing similar documentation for the Leningrad NPP assessment were presented, providing Novovoronezh representatives a perspective on scope of work, organization, and planning needed to complete the documentation. The group agreed that Novovoronezh staff will begin drafting the plan for the documentation effort. (Walter Pasedag, DOE, 301-903-3628; Phil Pizzica, ANL, 630-252-4847)

Electrogorsk Facility Receives Instrumentation To Aid in Validating Reactor Safety Computer Codes. On April 2, four sets of specialized instruments reached the PSB-VVER test facility in Electrogorsk, Russia. The PSB-VVER is an electrically heated model of a VVER-1000 reactor. Russian specialists will use the PSB-VVER in their work to assess and validate computer codes for evaluating the safety of VVER-1000 reactors.

Each of the four sets of instruments provided by the United States includes a gamma densitometer, used to measure pipe fluid density; a drag screen, to measure the fluid momentum flux; a stainless steel spool to which the densitometer and drag screen are mounted; and the required electronics and hardware. The instrument spools are to be inserted into the facility piping. Used in combination, these instruments will provide accurate data on the average fluid density, fluid velocity, and fluid phase description at the piping location at which they are mounted.

The equipment provided to the Electrogorsk facility consists of instrumentation and electronics used previously in U.S. experimental facilities at Idaho National Engineering and Environmental Laboratory. U.S. specialists redesigned and adapted the instrumentation for use in the Russian work at Electrogorsk. The redesign reduced the equipment cost by half, making it possible to provide advanced instrumentation that will enhance the accuracy of the Russian code assessment work. (Walter Pasedag, DOE, 301-903-3628; Mike Modro, INEEL, 208-526-9402)

RELAP5 Code Validation Projects Reviewed. Russian specialists working to validate the U.S.-developed RELAP5 computer code for use in analyzing the thermal-hydraulics of Soviet-designed reactors gathered in Electrogorsk on April 9 to review the status of their projects for the U.S. team. Participants discussed and finalized two reports documenting comparative assessments for the first two standard problems, one for VVER and one for RBMK reactors. The reports provide insights into the applicability of RELAP5 for modeling some phenomena characteristic of the Soviet-designed reactors. Russian specialists from the Russian International Nuclear Safety Center, the Electrogorsk Research and Engineering Center, and the Russian Research Center-Kurchatov Institute participated in the review with a U.S. team member from Argonne National Laboratory. (Walter Pasedag, DOE, 301-903-3628; Jordi Roglans, ANL, 630-252-3283)

^top

Ukraine

Simulator Design Reviews Indicate Projects Are on Schedule. During the week of March 29, specialists from DOE’s Brookhaven and Pacific Northwest national laboratories and GSE Power Systems, Inc., held a design review in Kyiv. GSE representatives presented the status of the preliminary design specifications (PDSs) for the full-scope simulators under development for Rivne Unit 3 and South Ukraine Unit 1. The national laboratory representatives verified that the designs specified were consistent with the contract technical specifications and that the nuclear power plant staff were satisfied with the specified designs. Design review completion represents a significant milestone for each project. (John Yoder, DOE, 301-903-5650; Peter Kohut, BNL, 516-344-1430; Joe Cleary, PNNL, 509-372-4094)

Simulator Instructors Receive Specialized Training. Plant staff from Rivne, South Ukraine, Zaporizhzhya, and Khmelnytskyy NPPs participated in a one-week training course at Khmelnytskyy NPP for simulator instructors April 5 through 9. With assistance from training specialists from the Engineering and Technical Center for the Training of Nuclear Industry Personnel, specialists from Sonalysts, Inc., presented the course, which covered techniques useful in the presentation of training materials using a full-scope simulator. This was the second presentation of the Simulator Instructor Training program to Ukrainian training specialists as part of the U.S. team’s simulator training and engineering support project. (John Yoder, DOE, 301-903-5650; Joe Cleary, PNNL, 509-372-4094)

Training Program Implemented at Zaporizhzhya. During the weeks of April 19 and 26, training specialists finalized and implemented the Unit Shift Supervisor pilot course at Zaporizhzhya NPP. Specialists from the Engineering and Technical Center for the Training of Nuclear Industry Personnel assisted Zaporizhzhya trainers with the course. Observers to the transfer included training specialists from Khmelnytskyy, Rivne, and South Ukraine NPPs and a DOE representative of the U.S. team. The implementation of this course marks the transfer of the second of two training programs to Zaporizhzhya NPP as part of the U.S. effort to transfer training technology to nuclear power plants in Ukraine. (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)

Quality Assurance Basis Developed for Plant Safety Work. Specialists from Khmelnytskyy NPP and its subcontractor, Kyiv Energoprojekt, completed the package of quality assurance project guidelines for use in the in-depth safety assessment work getting under way at Khmelnytskyy. U.S. team representatives from Science Applications International Corporation and Argonne National Laboratory reviewed the package and accepted it as complete on April 6. The package provides the basis for ensuring the quality of the technical work to be performed in the newly beginning Khmelnytskyy safety assessment. (Walter Pasedag, DOE, 301-903-3628; Charles Dickerman, ANL, 630-252-4622)

Key Databases Completed for Zaporizhzhya Safety Assessment. At the end of April, specialists from Joint Stock Enterprise-EIS issued reports documenting work completed recently on two databases:

  • Systems Description and Performance
  • Nuclear Steam Supply System.

The databases provide key information needed to complete a major part of the in-depth safety assessment under way at Zaporizhzhya Unit 5, namely, the Level 1 probabilistic risk assessment related to internal events that pose threats to safety. The descriptions of plant systems will provide the basis for performing the systems analysis associated with the probabilistic risk assessment. Information on the nuclear steam supply system will be used to develop the RELAP5 thermal-hydraulic model for the reactor system.

Under contract to the U.S. team, specialists from Joint Stock Enterprise-EIS carried out the database development work in Energodar, Ukraine, from August 1998 through April 1999. Scientech, Inc., provided technical assistance to Joint Stock Enterprise, while analysts from Energorisk, Ltd., and project managers from Zaporizhzhya NPP reviewed the work. Argonne National Laboratory representatives of the U.S. team reviewed the work for completeness.

Completion of the Level 1 internal events probabilistic risk assessment will provide the risk profile for the full-power operation of Zaporizhzhya Unit 5. It also will identify vulnerabilities in Unit 5 and identify potential major contributors to possible core damage. Zaporizhzhya NPP management also may use the assessment results in planning safety improvements for Unit 5. (Walter Pasedag, DOE, 301-903-3628; Christian Kot, ANL, 630-252-6151)

Ukrainian Customs Releases Safety Equipment for Delivery to Chornobyl Shelter. After languishing for almost a year in Ukrainian Customs, the bulk of the dose-reduction equipment was released in March to the Chornobyl Shelter. On-site training in the calibration and use of dose-reduction equipment and methods now is planned for completion in the April-September time frame. The gamma spectroscopy system still is in Customs, and portable radiation monitors are being shipped to Ukraine. The primary improvement still to be provided is an update of a whole-body counter in Slavutych. (Dennis Kreid, PNNL, 509-375-2170)

^top

Armenia

U.S. Training Methodology and Techniques Modeled for Armenia Specialists. Four training specialists from Armenia NPP spent three weeks during April touring U.S. nuclear power plant training centers and working with American specialists at Sonalysts, Inc., in Waterford, Connecticut. The visit was organized to provide the Armenian specialists firsthand observations of how U.S. specialists use techniques for training program development, such as the Systematic Approach to Training. That methodology is employed in the training program development efforts at Armenia NPP sponsored jointly by the International Atomic Energy Agency (IAEA) and DOE. Staff of Sonalysts, Inc., provided training materials and coordinated the visits to the plant training centers. The IAEA provided the financial resources for the visit. (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)

^top

Lithuania

Initial Shipments of Control-and-Protection System Upgrade Equipment Reach Ignalina. The U.S. Department of Energy and Ignalina NPP are collaborating in a cost-shared project to upgrade the backup control-and-protection system (DAZ 2) for Ignalina Unit 2. The purpose of the DAZ 2 is to back up the primary control-and-protection system to ensure that the plant shuts down properly when conditions warrant it. DOE is providing limited support (financial, engineering, and shipping of equipment) to the plant for this work. Ignalina NPP personnel are taking responsibility for all other activities, such as design and installation as well as development of the safety case for the system.

Initial equipment shipments for the DAZ 2 arrived at the plant site in early April. These shipments included sensors, conduit, cable, valves, and structural equipment. Ignalina workers will install the equipment during the Unit 2 maintenance outage scheduled for April through July 1999. The logic cabinets for the system are undergoing manufacture and assembly at the Foxboro Company. They will undergo factory acceptance tests in July before shipment to Ignalina for delivery during September 1999. (Norman Fletcher, DOE, 301-903-3275; Ron Wright, PNNL, 509-372-4076)

^top

Cross-Cutting Activities

New IAEA Program To Address Intergranular Stress Corrosion Cracking. In mid-April, the IAEA sponsored a meeting in Vienna focused on intergranular stress corrosion cracking (IGSCC) in RBMK reactors. April 12 through 15, the "Experts Group on Safety Assessment" meeting brought together regulatory authorities and designers from Russia, Lithuania, and Ukraine (the RBMK countries), as well as safety assessment experts from Germany, Switzerland, Sweden, the Czech Republic, the United Kingdom, and the United States. U.S. team representatives from Argonne and Pacific Northwest national laboratories participated.

Group members formed a steering committee and developed a plan for a new IAEA program to mitigate IGSCC in RBMK reactors. The plan addresses improvements in the performance and qualification of inservice inspections, comprehensive assessment techniques, qualification of repair techniques, and decontamination techniques. The IAEA anticipates funding the new effort as an extrabudgetary program. Elements of the effort are expected to complement DOE’s ongoing efforts to improve the safety of Soviet-designed reactors. (Tom Moran, ANL, 630-252-5901)

^top

Planned Activities

* indicates the event is a new item or has been changed from the last report.

* May 4-14 -- Rivne NPP, Ukraine

Training. Training specialists from Sonalysts, Inc., and the Engineering and Technical Center for the Training of Nuclear Industry Personnel will work with Rivne training staff to finalize learning materials and implement a training course (Unit Shift Supervisor) at the plant. Training specialists from Khmelnytskyy, South Ukraine, and Zaporizhzhya NPPs will participate as observers of the implementation. (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)

* May 10-21 -- Leningrad NPP, Russia.

Training. Training specialists from Sonalysts, Inc., and Leningrad trainers will collaborate to finalize learning materials and implement a training course (Control Room Reactor Operator) for plant staff. (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)

* May 10-21 -- Kola NPP, Russia.

Training. U.S. training experts from Sonalysts, Inc., and Human Performance Analysis Corp. will work with Kola NPP trainers to complete final preparations and implement a plant-specific training course, Motor-Operated Valves. (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)

* May 17-21 -- Kyiv, Ukraine

Ukraine Operational Safety Infrastructure. A U.S. team member from Pacific Northwest National Laboratory will conduct a workshop for specialists from the Nuclear Power Plant Operational Support Institute. The workshop will cover essentials of project management and the use of Microsoft Project to manage technical projects. The U.S.-provided project management tools will help improve the effectiveness of technical and scientific tasks performed by the institute for Energoatom and the nuclear power plant sites in Ukraine. (Lief Erickson, PNNL, 509-372-4097)

* May 17-28 -- Kursk NPP, Russia

Training. U.S. training experts from Sonalysts, Inc., and Human Performance Analysis Corp. will work with Kursk NPP trainers to complete final preparations and implement a plant-specific training course, Motor-Operated Valves. (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)

* May 24-28 -- Almaty, Kazakhstan

Kazakhstan Nuclear Safety Infrastructure Support. U.S. safety experts from Argonne National Laboratory will co-conduct a workshop with counterparts from the Republic of Kazakhstan at the Kazakhstan Atomic Energy Agency (KAEA) in Almaty. During the workshop, the experts will review the safety analysis report for packaging of BN-350 failed fuel. In addition to the careful review of the analysis, the Kazakhstani attendees will receive training on the methods for safety analysis review in the United States. Attendees are expected from several Kazakhstani nuclear organizations, including the KAEA, the Nuclear Technology Safety Center, the National Nuclear Center, and the BN-350 reactor at Aktau NPP. (George Imel, ANL-West, 208-533-7559)

* May 24-28 -- Waterford, Connecticut, USA

Training. U.S. training experts from Sonalysts, Inc., and Human Performance Analysis Corp. will attend an IAEA meeting on the training of nuclear power plant personnel on soft skills. The meeting will be held at the Northeast Utilities Millstone Training Center. The U.S. trainers will share experiences gained while working on training projects as part of the U.S. effort to improve safety at Soviet-designed nuclear power plants. (John Yoder, DOE, 301-903-5650; Joe Cleary, PNNL, 509-372-4094)

* May 24-28 -- Novovoronezh NPP, Russia

Engineering and Technology. The safety parameter display system for Novovoronezh Unit 4 will undergo site acceptance testing and official turnover to the plant. Participants are expected to include representatives of the U.S. contractors Science Applications International Corporation, Data Systems & Solutions, and Burns & Roe Enterprises, Inc. Representatives of Novovoronezh NPP, Rosenergoatom, Gosatomnadzor, and DOE also will participate. (Norman Fletcher, DOE, 301-903-3275; Rich Denning, PNNL, 614-424-7412; Frank Panisko, PNNL, 509-372-4472)

* May 24-28 -- Zaporizhzhya NPP, Ukraine

Engineering and Technology. The safety parameter display system for Zaporizhzhya will undergo site acceptance testing and be turned over to the plant. Participants are expected to include representatives of U.S. contractors Westinghouse Electric Company and Burns & Roe Enterprises, Inc. Representatives of Zaporizhzhya NPP, Energoatom, the Ukraine Nuclear Regulatory Administration, and DOE also will participate. (Norman Fletcher, DOE, 301-903-3275; Rich Denning, PNNL, 614-424-7412; Frank Panisko, PNNL, 509-372-4472)

* May 27-June 1 -- Kharkiv, Ukraine

Ukraine Economic Diversification. The United States will sponsor the second U.S.-Ukraine Conference on Energy Technology and Commercialization. The conference, a follow-on to the first held in Washington, D.C., in November 1998, will introduce U.S. corporations and firms to Ukrainian energy companies and institutes to expand business opportunities and promote commercial partnerships. Site visits will be organized to manufacturing and research facilities that are potential commercial partners for U.S. companies. Oil and gas company representatives also may visit the operating fields between Sumy and Kyiv. (Mike Congdon, PNNL, 202-646-5285)

* May 31-June 11 -- Armenia NPP, Armenia

Training. U.S. training experts from Sonalysts, Inc., will continue working with IAEA training specialists and training staff from Armenia NPP on development of training materials for two pilot training programs (Radiation Protection Technician and Senior Foreman for the Reactor Equipment Maintenance Shop). (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)

* May 31-June 11-- South Ukraine NPP, Ukraine

Training. South Ukraine NPP training specialists will finalize and implement the Unit Shift Supervisor course for the plant. Training specialists from Sonalysts, Inc., and the Engineering and Technical Center for the Training of Nuclear Industry Personnel will work with South Ukraine specialists to finalize learning materials and implement the course. Training specialists from Khmelnytskyy, Rivne, and Zaporizhzhya NPPs will participate as observers of the implementation. (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)

* June 7-11 -- Kyiv, Ukraine

Ukraine Operational Safety Infrastructure. The U.S. team will sponsor a workshop to develop a performance indicator program and related procedures for Ukraine’s nuclear power plants. Participants will include representatives from each nuclear power plant in Ukraine, Energoatom, the State Scientific and Technical Center, and the Nuclear Power Plant Operational Support Institute. A U.S. expert on the Nuclear Energy Institute/U.S. Nuclear Regulatory Commission risk-informed, performance-based inspection and enforcement program will present the most current U.S. approaches and will advise the Ukrainian participants in their procedure development. At the request of the Ukrainians, a U.S. expert involved in development of the performance indicator data collection software will advise on methods for collecting performance data. Energoatom will use the program and procedures resulting from this workshop to collect and evaluate performance data related to nuclear power plant safety. (Lief Erickson, PNNL, 509-372-4097; Don Draper, PNNL, 509-372-4079)

* June 14-19 -- Kyiv, Ukraine

Ukraine Operational Safety Infrastructure. A U.S. expert from Scientech, Inc., will conduct a workshop on decision analysis methods. Specialists from the Nuclear Power Plant Operational Support Institute will participate. The decision analysis tools are intended to help improve the effectiveness of technical and scientific tasks performed by the institute for Energoatom and the nuclear power plant sites in Ukraine. (Lief Erickson, PNNL, 509-372-4097)

June 14-18 -- Vienna, Austria

Cross-Cutting. The International Atomic Energy Agency's International Conference on the Strengthening of Nuclear Safety in Eastern Europe will review the results of national and international programs to enhance the safety of VVER and RBMK nuclear power plants. Additional specific information about the conference is available at http://www.iaea.or.at/worldatom/thisweek/preview/1999meet/infcn75.html

* June 14-25 -- Ignalina NPP, Lithuania

Training. U.S. training experts from Sonalysts, Inc., IAEA training specialists, and specialists from Ignalina NPP will meet to continue work on training materials for the pilot program, Mechanical Maintenance. (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)

* June 21-July 2 -- Kalinin NPP, Russia

Training. U.S. experts from Sonalysts, Inc., and specialists from Kalinin and Balakovo will review training materials, then implement a pilot Mechanical Maintenance training program for the plant. U.S. team members will participate in the pilot implementation. (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)

* June 21-July 2 -- Khmelnytskyy NPP, Ukraine

Training. U.S. experts from Sonalysts, Inc., will work with specialists from Khmelnytskyy NPP to review preparation of materials developed for a pilot Unit Shift Supervisor training program. During the second week of the visit, training specialists from Khmelnytskyy will conduct a pilot implementation of the program. U.S. team representatives personnel will participate in the pilot implementation. (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)

* June 22-25 -- Richland, Washington, USA

Training. The International Atomic Energy Agency and DOE will cosponsor a meeting, Evaluating the Effectiveness of Training for Nuclear Facility Personnel. Between 80 and 120 international training specialists are expected to participate. A member of the U.S. team from Human Performance Analysis Corp. will present data on performance measures used to assess the effectiveness of training technology transfer activities conducted as part of DOE’s work to improve safety at Soviet-designed nuclear power plants. (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)

October 12-14 -- Slavutych, Ukraine

Chornobyl Initiatives. The International Chornobyl Center will hold its annual conference, to facilitate the exchange of information on scientific and technical international cooperation at the Chornobyl site and on nuclear and radiation safety issues. The conference also seeks to coordinate and integrate efforts of the world community. Abstracts are due June 1, 1999. (Elena Tolkach, Secretary of the Organizing Committee, P.B. 151, Slavutych, Kyiv Region 255190, Ukraine, telephone: 38-(044)-79-23016; fax: 8-(044)-79-28144; e-mail: elena@chctr.pnl.gov)

^top

----------
Please write to us at insp@pnl.gov
About this Web Site

https://insp.pnnl.gov:80/?reports/activity/04_99
The content was last modified on 05/04/1999 .

Security & Privacy