Important Note: This website contains historical data from the INSP project. As of 2004 the site is no longer maintained and certain sections do not work correctly.
Activity Report
July 25, 1997 RUSSIAInstructor Skills Workshop Implemented at Novovoronezh Training Center. Training experts from the Balakovo and Novovoronezh training centers and the United States implemented the Instructor Skills Workshop during the week of July 21. Attendees included training personnel from each of the Russian nuclear power plants (NPPs) and training centers. After attending this workshop, the trainers at each site are better able to transfer this course to their own plants. (Sonja Haber, BNL, 516-344-3575) Research Institute for Atomic Reactors Starts Work on Training Course. Training specialists from the Balakovo training center and the U.S. team began work with Russia's Research Institute for Atomic Reactors (NIIAR) during July. The specialists are collaborating with NIIAR staff to develop training materials for the Shift Supervisor training course. (Sonja Haber, BNL, 516-344-3575) Soviet-Designed Reactors in Russia to Receive Nondestructive Evaluation Equipment. Equipment for performing nondestructive evaluations of reactor components is being purchased for all operating reactors at participating Russian NPPs. The equipment includes 25 compact flaw detectors, 25 hand-held digital thickness gauges, and 20 hardness testers. Diaprom, the Russian center for nondestructive monitoring and diagnostics, developed the specifications for the equipment purchase. Delivery of the equipment in Russia is anticipated for mid-September. (Greg Trosman, DOE, 301-903-3581; Tom Taylor, PNNL, 509-375-4331) Computer Equipment Ordered for Russian Reliability Database Development. In mid-July, computers to support data entry for the Russian reliability database effort were ordered. Delivery is expected by early August. (Tom Vehec, PNNL, 509-372-4072) Pilot Analysis of Fire Hazards Begins at Smolensk. Representatives of Rosenergoatom, Atomenergoproekt, VNIIAES, and Smolensk NPP met with U.S. team members during the week of July 14 to begin work on the safe shutdown study planned for Smolensk NPP. The effort at Smolensk is a pilot fire hazards analysis for all Russian plants with RBMK reactors. Bechtel National, Inc., will provide training on the analysis methodology starting in Moscow on August 18. Follow-up training and consultation will be held in October at the Smolensk plant. Equipment to support the analysis--including computers and a scanner, copy machine, and digital camera--will be delivered to VNIIAES around the end of July. Meetings to review the analysis results are planned tentatively for January, April, and July 1998. (Andrew Minister, PNNL, 509-376-4938) Installation Nears Completion for Kola Radiation Monitors. U.S. specialists from Brookhaven National Laboratory and Victoreen, Inc., recently worked with Kola NPP staff to complete the installation of the four-channel high-level confinement radiation monitor system in Kola Unit 2. Each of the four detector channels was calibrated electronically, and the output of each detector was verified with the cesium field calibrator. The Kola engineers were instructed and trained in these operation and calibration procedures concurrently with the system calibration by the Victoreen field service engineer. All four channels of the radiation monitor system now are installed, operating, and performing within specified tolerances. Improvements to some of the cable terminations, with the United States to supply the necessary hardware, will complete the project. These remaining tasks are expected to be accomplished by the Kola engineers prior to the end of the current outage for Unit 2. (George Greene, BNL, 516-344-2296) Installation Date Set for First Novovoronezh Safety Parameter Display System. The U.S. team recently made final plans to install a safety parameter display system in Novovoronezh Unit 3 in September. In preparation for that installation, factory acceptance testing of the system hardware will be conducted in early August at the Science Applications International Corporation test facility near Columbus, Ohio. After the test is completed, the integrated system will be shipped to Novovoronezh for installation during the fall outage. Upon completion of the test sequence at the plant, the system should be fully operational by early February 1998. (Mike Durst, PNNL, 509-372-4698) Regulatory Requirements for Circuit Breaker Certification Discussed. Regulatory requirements for certifying 400-volt and 6-kilovolt circuit breakers and associated equipment were discussed in a mid-July meeting in Moscow. Participants included representatives from Rosenergoatom, Gosatomnadzor, and Atomenergoproekt; Russian circuit breaker equipment suppliers ABB/Moselectro, ELOX, and Plant Progress; French circuit breaker supplier Groupe Schneider; Smolensk NPP personnel; and U.S. team representatives. The circuit breakers are being developed for use in Soviet-designed NPPs in Russia. In addition, information was gained on the required number and types of circuit breakers and how the circuit breakers would be installed at Smolensk for the licensing phase of the effort. The work at Smolensk will improve the safety of that plant by providing reliable safety-related circuit breakers. (Norman Fletcher, DOE, 301 903-3275) UKRAINEPlant Staff Receive Training in Simulator Verification and Validation. During the week of July 14, U.S. specialists from Brookhaven National Laboratory and General Physics Corporation presented a one-week training course on verification and validation procedures for nuclear power plant simulators. Training was presented at Khmelnytskyy NPP. Staff from Khmelnytskyy, South Ukraine, and Chornobyl NPPs and the Engineering Technical Center on Personnel Training for Nuclear Energy in Kyiv attended the training course. The course objective was to help the NPP staff in performing the verification and validation tasks for their respective NPP simulators. (Peter Kohut, BNL, 516-344-4982) Participants Review Khmelnytskyy Full- Scope Simulator Development. A review meeting was held in Neteshin, Ukraine, during the week of July 14 to discuss development of a full-scope simulator for Khmelnytskyy NPP. Staff from Khmelnytskyy NPP, GSE Systems, Inc., and the U.S. team discussed the acceptance test phase of the project and reached agreements on translation and maintenance activities that will provide vital support during the test period. (Peter Kohut, BNL, 516-344-4982) Khmelnytskyy Implements Eighth Training Course. During the week of June 23, staff of the Khmelnytskyy training center implemented the Control Room Reactor Operator course. General Physics Corporation specialists assisted with the implementation. Observers included training specialists from Chornobyl and Zaporizhzhya NPPs, the Engineering Technical Center on Personnel Training for Nuclear Energy, and training experts from the U.S. team. The course consisted of modules covering reactor and system fundamentals and operator administrative actions, as well as a full-scope simulator operational-event exercise. The course presentation marks the eighth and final implementation of training courses developed at the Khmelnytskyy training center. Establishment of the center and implementation of the plant-specific training courses are intended to lead to use of the Systematic Approach to Training throughout Ukraine. Work with Khmelnytskyy NPP will continue; U.S. specialists will collaborate with plant training staff in evaluating the training program and in transferring the methodology for the Systematic Approach to Training to other NPPs in Ukraine. (Sonja Haber, BNL, 516-344-3575) Coordinators Discuss Ukraine Training Technology Transfer. A coordination meeting on transferring training technology to NPPs in Ukraine was held on June 27 in Kyiv at the offices of the Engineering Technical Center on Personnel Training for Nuclear Energy. Participants included a representative from Derzhkomatom; training specialists from Khmelnytskyy, Zaporizhzhya, and Rivne NPPs; Engineering Technical Center staff; and U.S. training team representatives. Issues discussed and decisions made covered project funding, first working visit dates, and specifications for basic and course-specific equipment. (Sonja Haber, BNL, 516-344-3575) Chornobyl Implements First Training Course. Training staff from Chornobyl NPP presented the Chornobyl-specific Radiation Protection Technician training course during the week of July 14. U.S. training experts observed the presentation, which represented the first course implementation at Chornobyl. This pilot course will form the basis for more extensive training that will be developed for Chornobyl Shelter workers. (Sonja Haber, BNL, 516-344-3575) South Ukraine Technicians Pleased with Performance of New Equipment. In March 1997, the U.S. team delivered manual ultrasonic instruments to all NPPs in Ukraine. In late-July discussions with South Ukraine personnel concerning nondestructive evaluation (NDE) and testing, technicians indicated that they were extremely happy with the new instruments. They stated that the instrumentation was much more sensitive than that previously available for use at the plant. NDE technicians reported that they had used the new instrumentation to inspect the turbine blade attachments and had found several unacceptable cracks. Plant staff now are replacing those defective turbine blades. (Tom Taylor, PNNL, 509-375-4331) Computer Equipment Delivered for Ukraine Reliability Database Development. During the week of July 14, INIT, the primary contractor for the Ukraine reliability database project, delivered the required computer equipment within one week after receiving the U.S. team's purchase requisition. Work on actual database development is already under way. (Tom Vehec, PNNL, 509-372-4072) Plans Finalized for Installing First Safety Parameter Display Systems into Ukraine's VVER-1000 Plants. Plans for installing the first of 11 safety parameter display systems into NPPs in Ukraine were finalized in a meeting held in Kyiv in late June. The hardware will be installed into 11 operating VVER-1000 reactors in Ukraine, with the first two plant installations occurring at Zaporizhzhya Unit 5 and Khmelnytskyy Unit 1 in spring 1998. Because both units will be installed in parallel, U.S. contractors Burns & Roe and Westinghouse Electric Corporation are aggressively managing an expedited schedule. At the meeting, schedules also were established for the remaining nine units. The schedule includes completing the installation of all 11 units by 2001, with most of the technology for in-country work transferred by 1998. (Mike Durst, PNNL, 509-372-4698) CHORNOBYL SHELTER PROJECTSources of Radiological Protection Equipment Identified for Chornobyl Shelter. In mid-July, U.S. specialists evaluated excess radiological protection equipment at the Savannah River Site and the Federal Emergency Management Agency facility at Mt. Weather, Virginia, for possible use at the Chornobyl Shelter. The evaluation identified equipment that may be transferable to the shelter, pending approval by Chornobyl Shelter management. (George Vargo, PNNL, 509-375-6836) Remote Systems for Chornobyl Shelter to be Demonstrated. REDZONE Robotics has been selected to develop an initial robotics platform and instrument/tooling suite for a demonstration in the Chornobyl Shelter. REDZONE will be assisted by experts from Lawrence Livermore National Laboratory and a consortium including the National Aeronautics and Space Administration, Carnegie Mellon University, and Westinghouse Electric Corporation. The mission will focus on obtaining samples of concrete to determine the level of deterioration experienced in areas of the shelter subjected to high radiation dose and thermal histories. Nondestructive testing capabilities will be incorporated with coring capabilities to establish a correlation of results expected to minimize the number of core samples required. The shelter demonstration is scheduled for March 1998. (John Schmidt, PNNL, 509-372-6377) CENTRAL AND EASTERN EUROPEBulgaria: Scientist-Students Complete Basic Training on RELAP5. On July 23, eight scientists from Bulgaria successfully completed basic training on the RELAP5 computer code. Technical experts from two national laboratories presented the course in Idaho Falls, Idaho, to six staff from Kozloduy NPP and two from the Institute for Nuclear Research and Nuclear Energy in Sofia. Lectures introduced the RELAP5 code, and hands-on workshop exercises illustrated use of the code for performing thermal-hydraulic analyses of VVER reactors. Future joint activities in support of the Kozloduy NPP thermal-hydraulic safety analysis efforts now are being defined with the Bulgarian organizations in Sofia and Kozloduy. (Don Fletcher, INEEL, 208-526-7652; Ross Jensen, ANL, 208-533-7911) Hungary: Human Factors Emphasized in New Risk Characterization Effort. The Nuclear Safety Inspectorate arm of the Hungarian Atomic Energy Commission has directed Paks NPP to characterize risk at other than full-power conditions, with emphasis on operator performance and reliability. In response to this direction, an expert from Scientech, Inc., met in mid-July with staff of Hungary's Institute for Electric Power Research (VEIKI) in Budapest. VEIKI is the lead technical support organization for the Paks training center and Paks probabilistic risk assessments. The discussions covered human factors training and support. The meeting resulted in agreement on the overall task structure for the effort, a visit to the plant site to determine available records and data, and the development of a screening process to facilitate categorization of the data. (Bob Fitzpatrick, BNL, 516-344-7204) Slovakia: Workshop Held at Trnava Training Center. U.S. training specialists conducted a two-week workshop on the Systematic Approach to Training for staff of the Trnava training center. The workshop focused on the methodology and its application to the training materials, which will be developed in future working visits with Trnava staff. As part of this effort, Trnava training specialists will participate in a two-week course on Instructor Skills Training at General Physics Corporation facilities in Aiken, South Carolina, in late July. (Sonja Haber, BNL, 516-344-3575) PLANNED ACTIVITIES
*July 25-30 -- Rivne and Kyiv, Ukraine. *July 26-August 6 -- Vienna, Austria; Trnava,
Slovakia. July 26-August 9 -- Aiken, South Carolina,
USA. *July 28-August 8 -- Aiken, South
Carolina, USA. July 29 -- Moscow, Russia. *July 31-August 2 -- Yuzhnoukrainsk,
Ukraine. *August 1-9 -- Vienna, Austria. *August 2-17 -- Seattle,
Washington, USA. *August 3-8
-- Vilnius and Visaginas, Lithuania. *August 3-16 -- Columbus, Ohio,
USA. *August 4 -8 --
Aiken, South Carolina, USA. *August 4-12 -- Richmond, Virginia; Charlotte,
North Carolina, USA. *August 12-16
-- Kyiv, Ukraine. August 12-16 -- Slavutych, Ukraine. *August 15-24 -- Moscow and Kurchatov,
Russia. *August 18-22 -- Zaporizhzhya NPP,
Ukraine. * Date
changed to August 24-29 -- Kyiv, Ukraine. *August 25-29 --Trnava, Slovakia. August 25-September 4 -- Moscow, Russia. *September 1-5 -- Chornobyl NPP, Ukraine. *September 1-12 -- Novovoronezh
Training Center, Russia. *September 1-12 -- Novovoronezh NPP, Russia. *September 1-12 --
Kalinin NPP, Russia. *September 1-12 -- Kursk NPP, Russia.
September 1-12 -- Chornobyl NPP, Ukraine. *September
8-12 -- Oradell, New Jersey; Washington, D.C., USA. *September 8-19 -- Rivne NPP, Ukraine. *September
8-19 -- Zaporizhzhya NPP, Ukraine. *September 8-19
-- Kozloduy NPP, Bulgaria. *September 15-19 -- Sofia and Kozloduy
NPP, Bulgaria. *September 15-26 -- South Ukraine NPP,
Ukraine. *September 15-26 -- Argonne,
Illinois; Richland, Washington, USA. *September 22-October 3 -- Smolensk NPP, Russia. *September 22-October 3 -- Smolensk Training Center, Russia. *September 27-28 -- Smolensk Training Center, Russia. September 27-October 3 -- Helsinki,
Finland. *September 29-October 10 --
Bilibino NPP, Russia. *October 13-17 -- Vilnius and Ignalina NPP,
Lithuania. |
Please write to us at
insp@pnl.gov
About this Web Site
https://insp.pnnl.gov:80/?reports/activity/07_25_97
The content was last modified on
Wed Aug 27 10:00:51 US/Pacific 1997
.