Important Note: This website contains historical data from the INSP project. As of 2004 the site is no longer maintained and certain sections do not work correctly.
Chornobyl Report
The Chornobyl Report is a new biweekly publication that will feature status reports on cooperative efforts between the U.S. Department of Energy and Ukraine to address safety issues at Chornobyl. Among topics covered in the report will be U.S. support for
Status reports will include information on major work activities, key accomplishments, developing issues, and planned events relating to these initiatives. News items and comments can be directed to INSP Communications, (509) 372-6015, or e-mail susan.senner@pnl.gov. Joint activities advance through Chornobyl Center
Awaiting word on the PMU contractRepresentatives from Chornobyl nuclear power plant (NPP) and a proposal team consisting of Bechtel, ElectriciteŽde France, and Battelle staff are nearing agreement on contract negotiations for the Chornobyl Shelter Project Management Unit (PMU) Consultant assignment. Negotiations have been under way in Kyiv since mid-March under the surveillance of the European Bank for Reconstruction and Development (EBRD). EBRD will serve as the financial manager for the Shelter Project. Primary issues relating to responsibility for nuclear liability and insurance appear to be sufficiently resolved for closing the agreement, and there now is growing confidence that the PMU consultant contract will be signed by late April. Plans call for the next step in the Shelter Project, consisting of review and award of the early biddable project proposals, to be initiated immediately, tentatively by the end of April. Ukraine regulator seeks technical assistanceOn March 17, the EBRD and Chornobyl NPP received expressions of interest for a technical assistance project to support Ukraine's Nuclear Regulatory Administration (NRA). The work will involve assisting the NRA in managing the many demands anticipated during implementation of the Shelter Project. The EBRD is expected to issue a request for proposal to a short list of candidates by the end of April. More equipment on the way
Shelter staff recently communicated the need for an additional concrete saw and drilling equipment, and tools for the air compressor. Purchase requisitions for this equipment are in progress. Vent stack work on target for July completionUkraine, Canada, and the United States jointly are funding repairs to the external bracing and foundation of the Chornobyl Unit 3/4 ventilation stack, damaged heavily in the 1986 accident. The stack still is used during operation of Unit 3. A contract was placed with the Shelter in December 1997, specifying project management deliverables comprising five milestones as the basis for Canadian and U.S. payments for the repair equipment and actual work. Once repaired, the stack will be capable of withstanding Unit 3 design loadings. Work began in early April toward achieving Milestone 4 -- completion of 50 percent of the vent stack repair work. Milestone 4 work is scheduled for completion in early May, and is being performed concurrently with foundation repair work. Repairs to the vent stack foundation are anticipated to be less complicated than the bracing repairs.
Plans to complete Milestone 5 and wrap up small residual tasks, dismantle auxiliary equipment, and finalize paperwork will take the schedule to the late-July project completion date.
On-site verification of the Milestone 3 deliverables was performed during the week of April 13. Those deliverables were items necessary to begin mobilizing the large work force and start the actual repair work. The deliverables included final regulatory authority to proceed, updated radiological data reflecting reduced dose rates from installation of U.S.-supplied lead shielding blankets, completion of mockup construction, completion of the personnel and materials accessway, and delivery of all required repair materials and equipment. Joint payment by the United States and Canada to Chornobyl NPP provided for mobilization of the repair work force and initiation of Milestone 4. Chornobyl NPP completed its deliverables for the first two milestones in February 1998. Deliverables for Milestone 1 included bracing repair design documentation, project planning documentation, signed contracts with the constructor for materials and repair work, and regulatory approval to initiate preparatory work and baseline radiation surveys following repair site decontamination. Milestone 2 deliverables included approved purchase orders and delivery dates for the repair materials, design of foundation support repairs and incorporation of these repairs into the project planning and design drawings, and specifications for a mockup to train repair workers in maintaining personnel radiation exposures at levels as low as reasonably achievable (ALARA). Joint Canadian/U.S. payments were made to the plant after the deliverables were verified by the U.S. team. See also Chornobyl Initiatives/General Information on Chornobyl and the Biweekly Report Archive. |
Please write to us at
insp@pnl.gov
About this Web Site
https://insp.pnnl.gov:80/?reports/biweekly/biweek41798
The content was last modified on
08/25/98
.