Important Note: This website contains historical data from the INSP project. As of 2004 the site is no longer maintained and certain sections do not work correctly.

INSP Logo
Chornobyl Initiatives Reports and Publications Photo Library Nuclear Reactor Profiles and Accomplishments About our Program Web site sections
- Current Activity Report
- Activity Report Archive
- Current Chornobyl Report
- Program Reports
- Brochures/Fliers
- INSP Resource Center


Chornobyl Report
            A biweekly update of Chornobyl support activities for June 26, 1998


Ventilation stack regains full design strength


The repaired ventilation stack in all its glory.
U.S. and Canadian project coordinators are at Chornobyl this week to perform final acceptance of the completed repair work to the ventilation stack between Chornobyl Units 3 and 4. During the past three months, Ukrainian workers have replaced external bracing, welded "strongback" supports over dented vertical braces, and strengthened foundations to return the stack and its bracing to full design strength.

Completion of the ventilation stack repairs mark the first significant physical safety improvement at the Chornobyl Nuclear Power Plant (ChNPP) since the 1986 accident. The project was funded jointly by the U.S. Department of Energy, Canada, and Ukraine. Structural analysis, repair design, contracting, and project management activities were performed by Ukrainian organizations.

To commemorate this significant milestone, ChNPP officials are planning an on-site event in mid-July that will involve dignitaries from all three countries that funded the repair work.


Chornobyl workers perform final on-site welding.
damaged structural element
Reinforcement of a damaged structural element.
replacement brace
Lower junctions of the replacement brace.

PMU forges ahead on Shelter work

The Chornobyl Shelter Project Management Unit (PMU) continues to solidify its team in Slavutych. Efforts include developing program management plans and procedures; arranging for office space; coordinating communications, transportation, and other logistical needs; and securing housing for the PMU consultant staff.

In parallel, PMU teams of experts are evaluating proposals submitted by industry representatives on four Early Biddable Project (EBP) Packages. The purpose of the EBPs is to maintain project momentum during the mobilization and planning stages of the PMU. The EBPs involve preparing studies, collecting and evaluating data, preparing conceptual designs, and performing assessments that support key Shelter Project decisions and infrastructure development.

The following outlines the current status of the EBP evaluation process.

Package A - Civil Engineering Projects: Evaluations are complete, and negotiations are in progress with the candidate contractor at this time. Announcement of the contractor is expected by the end of June.

Package B - Operations and Monitoring: Evaluations are complete, and recommendation for the candidate contractor is awaiting approval by the European Bank for Reconstruction and Development (EBRD). Negotiations are expected to begin soon, with a contract award anticipated in early July.

Package C - Emergency Systems: Evaluations have been completed and submitted to the EBRD for approval in late June. Expectations are that the contract will be awarded in July.

Package D - Fuel Containing Material Management: Evaluations began this month, and the contract is expected to be awarded in late July or early August.

The PMU also is reviewing Ukrainian Shelter projects planned, proposed, and, in some cases, on hold while ChNPP management determines the projects' potential for inclusion in the overall Shelter Project.

Equipment continues to clear customs

Fall-protection devices to be used for industrial safety purposes at ChNPP recently cleared Ukrainian customs for site delivery. Anti-contamination coveralls and automated thermoluminescent dosimeters used to measure personnel radiation exposure also have been released by customs and delivered to ChNPP.

Additional industrial safety and radiation protection equipment remains in customs.

Slavutych Laboratory hosts international seminar

The Slavutych Laboratory for International Research and Technology was host this week to an international seminar on Environmentally Assisted Cracking of Nuclear Power Plant Austenitic Piping. Austenitic, or stainless, steel is commonly used in nuclear power plants because of its low corrosion properties.

Nuclear industry representatives from the United States, Germany, Switzerland, Sweden, Spain, Russia, and Ukraine, including engineering staff from ChNPP, participated in the week-long seminar, which was funded by the International Atomic Energy Agency.

New satellite tower to upgrade Slavutych Laboratory communications


Tower at the Slavutych Laboratory.
Ukrainian workers last week completed construction of a new tower on which the Slavutych Laboratory's antennae receiver will be relocated. In the receiver's present location, communications to and from the Slavutych Laboratory often were unreliable. Establishment of the new tower in an area adjacent to the Laboratory will eliminate the need for a microwave link, thus providing more reliable communications between the Laboratory and the rest of the world.

The receiver will be moved to its permanent location next week, and improved satellite communications are expected shortly thereafter.


See also the Biweekly Report Archives and Chornobyl Initiatives/General Information on Chornobyl


^top

----------
Please write to us at insp@pnl.gov
About this Web Site

https://insp.pnnl.gov:80/?reports/biweekly/biweek62698
The content was last modified on 07/16/98 .

Security & Privacy