Important Note: This website contains historical data from the INSP project. As of 2004 the site is no longer maintained and certain sections do not work correctly.
ArmeniaArmenia safety analysis data collection and model development discussedRepresentatives from the Slovakian Nuclear Power Plant Research Institute (VUJE), Armatom, the Armenia Nuclear Power Plant, and ANL met in late July to discuss issues related to data collection in support of thermal-hydraulics calculations for the Armenia plant. The main focus of the project is to carry out design-basis and beyond-design-basis accident analysis calculations with the RELAP5 thermal-hydraulics computer code. During this meeting, the participants addressed the collection of data needed to complete the modeling and concluded that most of the needed data either has been assembled or that reliable sources have been identified to develop the remaining material. Only two data areas were identified for which assistance will be required: 1) fuel and structural properties and 2) fuel design. Only the fuel supplier or another Russian organization that has access to the information (e.g., the reactor designer) can supply the fuel design data. Fuel and structural properties data could be obtained from the sources identified above or possibly from a VVER database, if one has been compiled. Collection of this data could prove challenging; however, the assessment will continue during the model development. The ANL representative met with a representative of the Technical Assistance to the Commonwealth of Independent States (TACIS) program, which is supporting the Armenia nuclear plant in developing improved emergency operating instructions (EOIs). TACIS also is supporting the development of a RELAP5 model to be used for the thermal-hydraulics calculations to verify the EOIs. A team at the University of Pisa is managing the model development work, and Gidropress is being contracted to carry out the calculations. Other cooperative efforts in this area are being investigated. In early August, Armatom, in cooperation with the Armenia plant, provided a data reference assessment report to VUJE, which then completed its own report by mid-August. A rudimentary RELAP5 model was produced several years ago under support from the U.S. Nuclear Regulatory Commission to simulate only the primary loop. This model will be the starting point of the current effort, and the model has been supplied to VUJE. A workshop for specialists from Armatom and the Armenia plant will be held this fall to continue development of the RELAP5 model. To prepare for this workshop, a nodalization scheme will be developed for the secondary loop. The goal is to produce a model validated against plant steady-state data by mid-December. (Walt Pasedag, NNSA, 301-903-3628; Phil Pizzica, ANL, 630-252-4847) Physical protection upgrades at Armenia plant reviewedA PNNL technical specialist met with representatives of the Armenia Nuclear Power Plant Physical Security Working Group in early August to review and discuss proposed design criteria for installation of short-term and long-term physical security needs and/or upgrades for the protection of identified critical nuclear facilities and activities at the plant. The group also reviewed the overall Physical Protections Upgrades Project and the newly installed Service Water System (SWS) for design compliance with national and international laws, regulations, and requirements, and recommended upgrades to the physical and technical security perimeter as necessary. Discussions included prioritization of upgrades and the possibility of integrating the SWS security upgrade project into the Physical Protection Upgrades Project. (Grigory Trosman, NNSA, 301-903-3581; Denver Greer, PNNL, 509-372-4839) Seismic inspection capability and proper safety culture established at Armenia plantIn early August, a representative from ANL visited the Armenia Nuclear Power Plant for a seismic safety inspection and to discuss safety assessment projects with Armatom, the Armenian technical support organization for the plant. The seismic inspection reviewed corrective actions taken since the previous inspection performed in September 2000, components that were not part of the September 2000 inspection, and examined components that require additional analysis to assess their safety. All findings from the September 2000 inspection regarding corrective maintenance, assessment of safe-shutdown procedures, and analysis to confirm that further corrective action is not needed have been addressed. Independent inspections performed in early 2001 resulted in implementation of necessary changes. This level of response indicates that INSP assistance has been influential in building a seismic inspection capability and a proper safety culture at the power plant. A final seismic inspection is planned during the plant outage in 2002. (Dennis Meyers, NNSA, 301-903-1418; Mark Petri, ANL, 630-252-3719) Preliminary Armatom internal web site establishedSoftware recently installed on Armatom computers enabled setup of a preliminary
internal web site that will become public once a final Internet connection is
established. A specialist from ANL met with representatives of the nuclear research
institute Armatom to discuss plans for a new partner web site located in Armenia
that will complement an existing network of INSC Armenia plant safety upgrade activities reviewedIn early September, representatives the Armenia Nuclear Power Plant, the U.S. State Department, Burns & Roe, and Battelle met to review the status of current projects and to discuss potential future projects in support of upgrading the safety of the plant. The plant currently is shut down for maintenance and refueling. Negotiations for the supply of fuel have been completed, and the plant is scheduled to return to power in mid-October. The following FY 2002 activities were reviewed.
In addition, a list of high priority future upgrade projects was developed. Burns & Roe will help determine upgrade costs and safety significance so that priorities can be established. (Dennis Meyers, NNSA, 301-903-1418; Richard Denning, Battelle, 614-424-7412) U.S. State Department representative visits Armenia plantMr. Warren Stern, U.S. State Department, and a representative of Battelle met with representatives of the Armenian Ministry of Energy and the Armenian Nuclear Regulatory Agency to discuss energy supply for the future in Armenia and for a tour of the Armenia Nuclear Power Plant. Deputy Energy Minister, Mr. Areg Galstyan, made a presentation that promoted the continued operation of the Armenia nuclear plant through at least 2008. (Dennis Meyers, NNSA, 301-903-1418; Richard Denning, Battelle, 614-424-7412) Simulator instructor meeting focuses on improved training materialsIn mid-September, a two-week working session that focused on Simulator Instructor Training Skills was held at the Armenia Nuclear Power Plant. During this working period, the plant's simulator instructors received training that will help them improve existing and future simulator training materials. Training specialists from the U.S. firm Sonalysts Inc. and from the Russian Institute for Nuclear Plant Operations led the course. (John Yoder, DOE, 301-903-5650; Don Draper, PNNL, 509-372-4079)
|
Please write to us at
insp@pnl.gov
About this Web Site
https://insp.pnnl.gov:80/?reports/activity/2001_11/2001_11armenia
The content was last modified on
02/08/2002
.