Kalinin Nuclear Power Plant

Kalinin Plant Operating History

Scope of DOE Activities

Accomplishments

Plant Manager: Stanislav I. Antipov
Chief Engineer: Vasily I. Aksenov
Utility: Rosenergoatom
Telephone No.: 7-082-55-44742
Fax: 7-082-55-44591


Reactor Type Net Output Initial Criticality Commercial Start
Unit 1 VVER-1000 950 MWe 4/1984 6/1985
Unit 2 VVER-1000 950 MWe 11/1986 3/1987
Unit 3 VVER-1000 950 MWe Under construction
Unit 4 VVER-1000 950 MWe Construction suspended
Kalinin Units 1 through 4
Udomlya, Tver, Russia
Pressurized Water Reactors (PWRs)
Utility: Rosenergoatom
Reactor Supplier: Mintyazhmash
Steam Generator Supplier: Kharkovsky Turbinny Zavod (Units l and 2); Leningradsky Metalichesky Zavod (Unit 3)
Architecture: Atomenergoproject
Construction: Ministry of Power Stations