Accomplishments

  • Twenty of 39 emergency operating instructions that promote safety through improved accident mitigation strategies for VVER-440/213 units were drafted.

  • Operator exchanges that provided plant personnel with knowledge needed to develop improved operating safety procedures and practices were completed.

  • Key components (e.g., computer platform, control panel, input-output control devices) for the VVER 1000 full-scope simulator at Unit 3 were delivered.

  • The in-depth safety assessment for Unit 3 was initiated.

  • Six advanced ultrasonic flaw detectors were delivered to the plant.

  • The transfer of the Systematic Approach to Training methodology and materials developed at the Khmelnytskyy Training Center has been initiated.

  • The transfer of the first job-specific training course has been initiated.

Rivne : | Operating History | Technical Activities | Accomplishments |


^top

----------
Please write to us at insp@pnl.gov
About this Web Site

https://insp.pnnl.gov:80/?profiles/rivne/ri_accomplish
The content was last modified on 01/25/99 .

Security & Privacy