Important Note: This website contains historical data from the INSP project. As of 2004 the site is no longer maintained and certain sections do not work correctly.
Russia
A joint venture agreement between Splav (Russia) and Target Rock (Curtiss-Wright, United States) has been signed for the manufacture and distribution of the solenoid valves. Leningrad NPP is interested in the purchase of approximately 20 valves. The first step in obtaining Russian certification will be the manufacture of two valves at Target Rock for use in the feedwater system at Leningrad NPP. After the completion of the pilot phase, valves will subsequently be manufactured at Splav. The solenoids will continue to be provided by Target Rock. (Richard Denning, BCO, 614-424-7412; Greg Trosman, NNSA, 301-903-3581)
Earlier this fall, specialists from PNNL met with representatives from the SCC and MCC to be updated on efforts to gain tax exemption status. The combines have reached a temporary verbal agreement with the tax ministry to not be assessed VAT until all the paperwork has been finalized. PNNL had been asked to withhold payments before the tax issue was resolved, but will now begin paying on completed invoices. Deliverables from each combine were also reviewed. A discussion was held on the second day of the meetings about the October site visit to Seversk. The second contract review meeting with SCC and MCC was held in late October within the Closed Administrative Territorial Formation of Seversk. A baseline inspection of the Seversk TET plant was conducted and PNNL specialists met with SCC TETs management and staff. The group toured the new, partially constructed coal handling system and inspected the water treatment facility. During the tour, the U.S. team was shown a renovated room that is to be the workspace for the U.S. technical oversight team during refurbishment activities. The U.S. team and TET representatives toured the boiler house, turbine generators, heat exchangers, water treatment facility, and control room to visibly inspect the equipment and facilities planned for refurbishment. Photographs of the equipment and facilities were taken to document their current condition. The MCC and SCC contracts, deliverables, and schedules were reviewed, including cost estimates. The third Contract Review Meeting was held at the International Building of Minatom on November 28-29. Contract deliverables were discussed and progress was assessed. The SCC gave a presentation on the Russian Federation Civil Engineering Norms and Standards. Re-negotiations began with the MCC on the details of where the TET site will be built. (Julian Hill, PNNL, 703-413-7801; Jim Mulkey, DOE, 301-903-5481)
The Leningrad Unit 2 ISA project was reviewed. With the project nearing completion, a summary report was prepared and reviewed for completeness. The technical committee reviewed the Leningrad Unit 1 ISA project. The scope of work was based in part on the experience of the Unit 2 project. Labor issues and timeline were also discussed and determined to be viable. The Leningrad NPP EOI project planning committee meeting was the first in a series supporting the development of risk informed EOIs. The meeting's primary objectives were to discuss the project's basis, scope, timing, and participants. The results of the recently completed Leningrad NPP Unit 2 ISA were reviewed and they indicated risk informed EOIs would contribute 82% of the forecast reduction in the core damage frequency presented in chapter 9 of the Unit 2 ISA summary report. The Lithuanian participants discussed their recent EOI experience and offered suggestions to improve Leningrad NPP's EOI project. All agreed that the Leningrad NPP EOI project would significantly benefit from the Ignalina NPP EOI program. Leningrad NPP will re-sequence their proposed scope of work based on Ignalina NPP insight. PNNL agreed to consider funding near-term technical support for Leningrad NPP EOI development groups. Leningrad NPP was expected to provide an updated project description by the end of 2001. (Sam McKay, PNNL, 509-372-4059; Walt Pasedag, NNSA, 301-903-3628; Dennis Meyers, NNSA, 301-903-1418)
|
Please write to us at
insp@pnl.gov
About this Web Site
https://insp.pnnl.gov:80/?reports/activity/2002_02/2002_02russia
The content was last modified on
02/12/2002
.